1 Chandos St Remedial Works
Delivering staged basement remedial works within an active commercial heritage building
Scope of works:
- Multi-level basement remedial works, delivered in two stages within an occupied commercial heritage building.
- Stage 1 – Early Works:
Removal of existing perimeter block walls within the carpark.- Installation of a temporary perimeter wall to maintain AC plenum functionality.
- Redirection of essential building services.
- Stage 2 – Main Works:
- Demolition of temporary plenum walls.
- Construction of shotcrete shoring reinforcement walls.
- Installation of new steel columns between each existing pier.
All works were staged to maintain continuous car park access, with an after-hours delivery schedule to minimise disruption to the occupied office tower above. Restricted site access required coordinated traffic management, and a specialised concrete delivery system was implemented to manage volume and placement constraints.
Year:
CommercialLocation:
Sydney, NSWDuration:
1 – 6 weeks | Stage 2 – 4 months